November 23, 2026
.png)
Cobalt Energy Project Services Limited (CEPSL) recently achieved Mechanical Completion at a Battery Energy Storage System (BESS) in the North West, on schedule and without complication.
BESS plants are a vital component in the UK’s path to net-zero, enabling for the storage of energy that has been captured from renewable sources. Contracted as the engineering, procurement and construction (EPC) contractor for the Civil and Electrical Balance of Plant (BoP), Cobalt was the responsible party for achieving Mechanical Completion on this project.
Despite numerous stages facing the CEPSL team, all objectives were successfully completed. Firstly, through the Civil BoP package, including all earthworks, foundation and infrastructure installations. This was followed by the mechanical installation of the battery technology equipment, a large-scale operation involving crane machinery. Last of all, the Electrical BoP was concluded, where further electrical cables and equipment vital to the site were carefully installed and tested.
%20(10).png)
Despite the complexity of this undertaking, Cobalt was able to achieve Mechanical Completion on time, with no accidents, and has since been awarded its Certificate of Mechanical Completion. This outcome is a milestone that marks the end of the construction phase, and is reflective of Cobalt’s overall efficiency, competency and keen attention to detail in running BESS and construction projects.
The project can now progress to the commissioning phase of the battery technology provider under the Cobalt Electrical Safety Rules.